沉管浮运检测和监测系统构建
郭强1,梁志伟2
(1.上海交通大学 上海交大海科(集团)有限公司, 上海 200240;  2.交通运输部广州打捞局, 广州 510260)
 
 
 
Construction of a Testing and Monitoring System in the Hauling of Immersed Tube Tunnel
GUO Qiang1,LIANG Zhiwei2
(1.Hike (Group) Co. Ltd, Shanghai Jiaotong University, Shanghai 200240, China; 2.Guangzhou Salvage Bureau of the Ministry of Transport, Guangzhou 510260, China)
全文: PDF(0 KB)  
输出: BibTeX | EndNote (RIS)      
摘要 
将沉管拖运过程作为一个融合了研究对象和周围环境的系统,重点从管段结构、地形等关键数据处理、模拟系统框架搭建方法及相关算法等方面进行研究,解决了管节拖运的过程模拟、路线优化、事故预报和追踪等问题.通过工程应用及与已有方法的成果进行对比,验证了该方案及其所用方法的可行性、正确性和优越性.
 
 
服务
把本文推荐给朋友
加入引用管理器
E-mail Alert
RSS
作者相关文章
Abstract
This paper regarded the tube hauling process as a system involving its circumstance, and analyzed the data processing, system frame construction, the relevant arithmetic and the realization of  the mathematical simulation, route optimization, risk prediction in the tube hauling process.  The methods proposed in the paper were used in practical engineering and its feasibility, correctness and superiority were verified.
收稿日期: 2013-02-15      出版日期: 2013-10-30
ZTFLH:  U 459.5  
引用本文:   
郭强1,梁志伟2. 沉管浮运检测和监测系统构建[J]. 上海交通大学学报(自然版), .
GUO Qiang1,LIANG Zhiwei2. Construction of a Testing and Monitoring System in the Hauling of Immersed Tube Tunnel. J. Shanghai Jiaotong Univ.(Sci.) , 2013, 47(10): 1606-1610.
链接本文:  
http://www.qk.sjtu.edu.cn/jsjtunc/CN/      或      http://www.qk.sjtu.edu.cn/jsjtunc/CN/Y2013/V47/I10/1606
[1]潘永仁.上海外环沉管隧道大型管段浮运方法[J].施工技术,2004,33(5):5254.

PAN Yongren.The floating transport method of large elements employed for shanghai outring immersed tube tunnel[J]. Construction Technology, 2004,33(5):5254.




[2]麦继婷,关宝树.用Morison方程计算分析悬浮隧道所受波浪力初探[J].石家庄铁道学院学报,2003,16(3):14.

MAI Jiting, GUAN Baoshu. A preliminary calculating analysis of the wave forces on a submerged floating tunnel by applying the Morison equation[J]. Journal of Shijiazhuang Railway Institute, 2003, 16(3): 14.

[3]潘永仁,丁美.大型沉管隧道管段沉放施工技术[J].现代隧道技术, 2004, 41(5): 15.

PAN Yongren, DING Mei. Immersed tunnel sinking pipe construction technology[J]. Modern Tunnelling Technology, 2004, 41(5): 15.

[4]彭红霞,王怀东.仑头生物岛沉管隧道管段浮运方案探讨[J].隧道建设,2007,27(4):8588.

PENG Hongxia,WANG Huaidong. Discussion on tube element towing options for luntoushengwudao immersed tunnel project[J]. Tunnel Construction, 2007,27(4):8588.

[5]詹德新,张乐文,赵成璧,等.大型管节水面浮运及沉放数值模拟和可视化实现[J].武汉理工大学学报:交通科学与工程版,2001,25(1):1620.

ZHAN Dexin, ZHANG Lewen, ZHAO Chengbi, et al. Numcrical simulation and visualization of immersed tube tunnel maneuvering and immersing[J]. Journal of Wuhan University of Technology: Transportation Science &Technology,2001,25(1):1620.

[6]王艳宁,熊刚.沉管隧道技术的应用与现状分析[J].现代隧道技术,2007,44(4):14.

WANG Yanning, XIONG Gang. Application and state of the art of immersed tube tunnels[J].

Modern Tunnelling Technology,2007,44(4):14.

[7]赵思齐.用于沉管施工的实时定位系统开发及应用[D].上海:同济大学土木工程学院,2007.

[8]Aono T, Sumida K, Fujiwara R, et al. Rapid stabilization of the immersed tunnel element[C]∥ Proceedings of the Coastal Structures 2003 Conferenee.  Portland, Oregon: ASCE, 2003: 394404.

[9]陈智杰.波浪作用下沉管管段沉放运动的试验与数值研究[D].大连:大连理工大学海岸和近海工程国家重点实验室,2009.

[10]Kasper T, Steenfelt J S, Pedersen L M, et al. Stability of an immersed tunnel in offshore conditions under deepwater wave impact[J]. Coastal Engineering, 2008, 55(9): 753760.


 