Float over Method Application for 2.5WM Wind Turbine Integral Removal in Guanting Reservoir

  • YU Lei ,
  • GAO Zhizhao
Expand
  • Global Offshore Engineering(Tianjin) Co., Ltd., Tianjin 300452, China

Online published: 2024-01-06

Abstract

In inland reservoirs and lakes, the integral removal technology of wind turbines is currently blank in China, As the conventional technology and equipment used for offshore wind turbine disassembly cannot be used. in order to solve the problem of Goldwind Technology produced 2.5WM wind turbine removal in Guanting Reservoir, a float platform assembled by some pontoons at temporary wharf, the temporary wharf built by dredging on the shore, the single pontoon is prefabricated in the factory and the transport to wharf where assembled one by one to form a floating platform. The floatover integral removal technology applied in extremely shallow water depth, which improves construction safety, saves materials and construction time, and is convenient for demolition. This paper introduces the design idea and engineering practice of integral removal of wind turbine by floatover method, hopes can provide reference for similar projects.

Cite this article

YU Lei , GAO Zhizhao . Float over Method Application for 2.5WM Wind Turbine Integral Removal in Guanting Reservoir[J]. Ocean Engineering Equipment and Technology, 2023 , 10(4) : 52 -58 . DOI: 10.12087/oeet.2095-7297.2023.04.08

Outlines

/