Ocean Engineering Equipment and Technology ›› 2015, Vol. 2 ›› Issue (1): 55-59.

• Orginal Article • Previous Articles     Next Articles

Research on Assembly Process of All Slewing Floating Crane

Yang BAI, Zhi-lin GAO, Zheng-quan XUE   

  1. Offshore Oil Engineering Co., Ltd., Tianjin 300451, China
  • Received:2014-12-23 Online:2015-02-20 Published:2016-03-31

Abstract:

Offshore oil development project relies on floating crane. On "HYSY201" deepwater pipe-laying crane vessel, the 4000 t all slewing floating crane is designed according to European standards. Its building and assembly are precision, difficult and complex, and the assembly quality directly affects the performance of the floating crane. The key technologies including assembly procedure, precision measurement, virtual assembly, tooling design, and lifting are introduced in detail. The general assembly process for such floating cranes are discussed.

Key words: all slewing floating crane, assembly process, precision measurement, virtual assembly, tooling design