Offshore oil development project relies on floating crane. On "HYSY201" deepwater pipe-laying crane vessel, the 4000 t all slewing floating crane is designed according to European standards. Its building and assembly are precision, difficult and complex, and the assembly quality directly affects the performance of the floating crane. The key technologies including assembly procedure, precision measurement, virtual assembly, tooling design, and lifting are introduced in detail. The general assembly process for such floating cranes are discussed.
Key words: all slewing floating crane, assembly process, precision measurement, virtual assembly, tooling design
CLC Number:
U445.467
Yang BAI, Zhi-lin GAO, Zheng-quan XUE. Research on Assembly Process of All Slewing Floating Crane[J]. Ocean Engineering Equipment and Technology, 2015, 2(1): 55-59.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.qk.sjtu.edu.cn/oeet/EN/
https://www.qk.sjtu.edu.cn/oeet/EN/Y2015/V2/I1/55
Fig.1
Structural schematic diagram of all slewing floating crane
Table 1
Technical parameters of main components of all slewing floating crane
Fig.2
Assembly process of all slewing floating crane
Fig.3
Structural arrangement of slewing system
Fig.4
Schematic diagram of the lifting of A-frame